Bank of America

Requirement

Bank of America Merrill Lynch required replacement of the chilled water system. It was a prerequisite of the contract that a chilled water service was in service throughout the entire implementation and there were no unplanned shutdowns to the chilled water system.

Solution

SPIE were appointed by BAML for the role of principal contractor to remove 7 chillers and install 8 replacement Excel Chillers.

The majority of the works needed to be carried out during banking hours with only major mobile crane lifts completed at weekends.

To ensure the project was a success SPIE executed the following works:

Access control within plant area,

Liaising with maintenance provider to allow scheduled maintenance to be carried out

Welfare of our personnel

Temporary removal of roof beams and louvres

New and modified plinths

Relocation of induction coupling

Temporary chilled water system within the basement